Rehabilitation with technological renovation of the supporting bearings in HPP Vau i Dejës
In October 2021 the rehabilitation in Ag.4 was successfully completed and at the end of December 2021 the rehabilitation with technological renewal of the supporting bearings in Ag.2 was completed. In total the rehabilitation of 3 aggregates was completed, including Ag.5 which was rehabilitated during 2020. By 2022, Ag.1 and Ag.3 remain to be rehabilitated, thus concluding the contract according to the foreseen deadlines.